Monday, August 1, 2011

Construction Update - July 2011

Issaquah Highlands – 3 Duplexes
Building 3: Built and laminated kitchen countertops, cut wood back splash, exterior paint prep on front porches, continued interior touch ups and hardware

Building 4: Cut wood back splash, continued grading in front, exterior paint prep on front porches, irrigation in front was installed, installed phone conduits

Dedications for these four homes set for Sat. August 27 at 3:00 PM.

Work continues on the last duplex:
Building 5: Framed landing on 5B, prep in front for setting post and beams, framing materials for next floor were delivered.

Next week we will continue with interior finish work, building block walls and taking care of exterior grading issues on 3 & 4. Framing will continue on building 5.


La Fortuna, Renton –multifamily buildings
Building #5 – six townhouses
We finished the fire rock and firing strips above the roofs and will be ready for the roof to be stocked on Tuesday. Framing punch list work continues and might wrap up next week.

Windows were delivered on Friday and secured in the back of a garage. Installation will begin after housewrap is completed.

Building #7- five townhouses
Complete Concrete worked on the footings and they passed their inspection on Thursday and poured on Friday. They will start the walls on Monday and hope to pour late in the week. The sewer and water sleeves were installed by volunteers before the pour.

Work next week will include; framing punch-list, exterior foam board, housewrap, windows, and wetlands mitigation.