Tuesday, December 20, 2011

Construction Update- December

La Fortuna, Renton

December 17th, 2011

This morning we had 3 Americorps CVLs call in sick and 1 more on vacation. Kristina and I both took work crews and Marla just happened to be coming out and led another crew, plus 2 family members worked on a project they had started last week without further supervision. Jahna also helped when she wasn't doing volunteer hospitality things. 22 of the 15 vols scheduled showed up making it rather exciting.

LF5-

Siding continues with Hardi- panel on the 3rd floor and over the low roofs in the back. We are nearing the time when we will need to tear down the scaffolding in the rear and move it out front to work there.

Electrical is still waiting for journeymen to come out. Jahna has a contact who might be available to help out.

LF7-

All of the stairs are in. Unit "e" has all of the exterior walls are up and the partywalls are framed, sheeted, and fire rocked. Unit "b" has 1 partywall ready to stand and all of the front and back walls up.
Work next week will include; framing, siding, and maybe painting?

December 10th, 2011
 
What a week! We were inundated with tools after the news stories on the radio and KOMO- TV. The response was amazing.

LF5-

Siding continues with panel on the third floor in the back and some plank on the north end and front. The belly band at the third floor has been completed, encircling the entire building. With this belly band finished we can now complete the last of the window trim on the third floor.

We failed gas piping inspection in 2 units and still haven't had a fire sprinkler inspection.

The journeymen electricians didn't make it in this week, so the electrical rough- in has not progressed.

LF7-

We had another Microsoft house day and got the partywall closed up, Strong- Walls installed. Asa and Josh came out on Saturday and framed a couple of walls on the ADA.

We finished floor framing on "b", guardrails,  sheeted the floor, started walls and put in the stairs. "E" has three walls up and another long wall started. "D" has one partywall framed, sheeted, fire rocked and 1/2 stood. "C" has some plates cut and ready to start framing.
Work next week will include; wall framing, siding/trim, electrical rough- in (depending on journeyman availability), framing punchlist, and draft blocking.

December 3rd, 2011

LF5-

Siding continues with siding across the front at ground level and on the north end on the second floor. Trim has started on the third floor on the front.

HVAC is complete and passed the duct blaster test and is scheduled for inspection.

Wiring is 99% in unit 6 and started in unit 5. We currently have 2 journeymen committed to Wednesdays and 1 apprentice who is working at IH when we don't have supervision. We are going to reach out to the Geek Squad team that came out last summer to work on the low voltage.

LF7-

Framing continues with 3 units sub- floor completed and another has the floor joists and beams in and blocking started.

Kip put in the temporary steps at the front doors of all 4 units. LF7e has a complete set of stairs to the 2nd floor, "d" has the stringers cut and rready to install, "c" has the landing completed and ready for stairs to begin, and "b" has the landing started.

The ADA unit was started by a Microsoft group on Wednesday and the partywall is framed and sheeting started. There is another group coming next week to continue framing.

Work next week will include; wall framing, floor sheeting, siding and trim, electrical rough- in, and framing punchlist.

 
Issaquah Highlands

December 17th, 2011

This week we had a series of inspections. The electrical, communications wiring and framing all passed. Insulation started in the garages with the ceilings and party wall. OSB was also installed on the party wall. We continued sealing the building with foam and caulking as we look for ways to improve our air leakage. Sheet rock was stocked in the building. Next week the ceilings will be installed and more foaming will be done in the attic. After the holidays we will be testing the building for air leakage and then proceeding with insulation and sheet rock.

On the exterior we shifted and removed some scaffolding. Decent weather allowed us to have several paint crews on Saturday. The south side of the building is now finished.

Next week Marc will begin trenching for utilities on the south end, removing additional scaffolding and continue with the foaming.
December 10th, 2011

The mechanicals for building 5 are complete. HVAC passed inspection and the Energy Star duct testing. The electrical and communication wire was finished on Friday and will be inspected early next week.

Siding for the building is complete except for an area over the main roof. A lot of effort went into caulking and foaming areas inside the units to help seal the building against air leakage. We also worked on punchlist items to get the building ready for framing inspection next week.

Next week we will continue with air sealing, insulating and closing up the party wall and hopefully be able to start insulation in the garages and some other areas of the building.

December 3rd, 2011

Good progress over the last week and a half in Issaquah.

On the exterior we've been continuing with siding, exterior paint prep and even a small amount of exterior paint. There are only two areas left to be sided, a portion of the front gable and a small field over the main roof. The soffits in the back were installed and the porch ceiling on 5A was insulated and installed.

On the inside we the plumbing system passed inspection, as did the gas piping. The HVAC contractor decided to change the design of the main duct system. They were nearly complete and have been removing and replacing duct work. Hopefully they will finish by the middle of next week and we will be able to have the system inspected and tested. Electrical rough-in started just before Thanksgiving and continued all of this week. 5B is about 90% complete and 5A is at 75% completion. We also started installing boxes, drilling and running conduit for the phone, cable and internet wiring. On Saturday, volunteers started sweeping out the units and caulking sill plates to better seal up the homes.

Next week we will continue with siding, wiring and exterior paint.




1 comment: