Monday, May 16, 2011

Construction Update May 16, 2011

La Fortuna, Renton
Habitat EKC and SKC welcome 45 additional AmeriCorps from all over the country for the AmeriCorps Build-a-Thon this week!

Unit #1
Needs guardrails and sub- floor can start.
Some sheetrock backers and party wall blocking still is needed.

Unit #2
Stairs in, guardrails up, floor sheeted, exterior plates cut and laid out. Ready to frame.

Unit #3 Joists in and rim joists 90% complete.

Unit #4 Guardrails up, floor sheeted, lines snapped, and stair landing in with the stair jacks cut.

Unit #5 Rim board, sheetrock backers, and blocking done. Ready for subfloor.

Unit # 6 Guardrails up, floor sheeted, stairs in, lines snapped, and exterior plates started.

Work this week:
Guardrails, stairs, floor sheeting, plus exterior, party, and interior walls.
Some site work: erosion control, street sweeping, and wetlands mitigation tasks.

Magnolia Village, Issaquah
Building 3:
Sheet rock finish complete.
Interior painting started in bathrooms and laundry room.
Exterior painting continued on the front.
Utility trenching continued.

Building 4:
Completed tile underlayment for both units.
Started setting tile in bathrooms and laundry.
Continued mill work  caulking.
Continued exterior painting on the front.
Building 5:
Completed interior walls of main floor.
Installed tie plates.
Worked on fire blocking and cabinet blocking.
Worked on installing 2x2's on concrete walls.