Habitat EKC and SKC welcome 45 additional AmeriCorps from all over the country for the AmeriCorps Build-a-Thon this week!
Unit #1
Needs guardrails and sub- floor can start.
Some sheetrock backers and party wall blocking still is needed.
Stairs in, guardrails up, floor sheeted, exterior plates cut and laid out. Ready to frame.
Unit #3 Joists in and rim joists 90% complete.
Unit #4 Guardrails up, floor sheeted, lines snapped, and stair landing in with the stair jacks cut.
Unit #5 Rim board, sheetrock backers, and blocking done. Ready for subfloor.
Unit # 6 Guardrails up, floor sheeted, stairs in, lines snapped, and exterior plates started.
Work this week:
Guardrails, stairs, floor sheeting, plus exterior, party, and interior walls.
Some site work: erosion control, street sweeping, and wetlands mitigation tasks.
Building 3:
Sheet rock finish complete.
Interior painting started in bathrooms and laundry room.
Sheet rock finish complete.
Interior painting started in bathrooms and laundry room.
Exterior painting continued on the front.
Utility trenching continued.
Building 4:
Completed tile underlayment for both units.
Started setting tile in bathrooms and laundry.
Continued mill work caulking.
Continued mill work caulking.
Continued exterior painting on the front.
Building 5:
Completed interior walls of main floor.
Completed interior walls of main floor.
Installed tie plates.
Worked on fire blocking and cabinet blocking.
Worked on installing 2x2's on concrete walls.