Construction Update April 4, 2011

La Fortuna, Renton 
Unit 1 has guardrails complete, stairs functional, and wall plates/layout started.

Unit 2 has exterior walls front and back, party walls framed and sheeted, and is waiting for inspections.

Unit 3  - floor sheeting 95% complete. Stairs 75% complete.

Unit 4 has floor framed, blocked, and ready for sub- floor.

Unit 5 has beams set and floor joists 85% complete.

Unit 6 has back wall standing and front walls 90% complete.

Work this week:
Floor joists/ blocking.
Floor sheeting.
Wall framing, stairs.
Wetlands mitigation.


Magnolia Village, Issaquah
Building 3:
Electrical rough-in is about 90% complete. Low voltage/communications wiring will start next week.
HVAC was completed and passed inspection.
Siding continued on the front gable and stairwell wall.
Staged scaffolding.
                
Building 4:
Completed insulation. Passed all inspections.
Communications wiring passed inspection.
Built scaffolding on the porch roofs and started siding above the roofs.
Installed OSB on interior shear wall.
Sheet rock is scheduled for delivery on Tuesday 4/5.

Building 5:
Framed interior party walls for both units.
Installed garage posts on 5A. Ready for beams.
Installed blocking on party walls for OSB sheathing
Joists were delivered.

Work this week:
We will continue siding on the fronts of buildings 3 and 4.
We will also continue exterior painting.
Electrical will hopefully finish up on building 3 and fire stopping should begin.
Sheet rock should begin on building 4. 
Framing will continue on building 5 with wall sheathing, beams and possibly joists.